Circular 8.3 Maintenance of Way - Ballast Operations

Western Washington Short Line
Office of the General Manager
100 Railroad Avenue
Monetesano, Washington

CIRCULAR NUMBER: 8.3                                                                 DATE: January 1, 1955

MAINTENANCE OF WAY
Ballast Operations

BY AUTHORITY OF:


S.B.Clinard
President and General Manager
___________________________________________________________________________________

Ballasting.-lt is the practice of most railways to raise or lift a ballasted track from 2 to 4 in. or more every few years. There are several reasons why this is done. (a) The work of general surfacing is done most easily by lifting the track and putting in a certain amount of new ballast. (b) There is also a certain settlement of the track resulting from disin­tegration and packing of the ballast and a loss of ballast over the shoulders and by being worked into the roadbed. (c) Old ballast becomes dirty and drains poorly. The common way, though not necessarily the best way, to improve the drainage is to lift the track and put a layer of fresh ballast over the old. (d) A further reason is that the weight of equipmer.t and amount of traffic has gradually increased on most roads and from time to time it has been necessary to increase the depth of ballast under the tie.
Before the new ballast is distributed, all unsuitable material above the bottom of the ties should be removed to the full width of ballast and used to widen narrow embankments; defective ties should be replaced, all ties respaced, and the track brought to perfect line by track-center stakes set by the engineer or by track-center monuments. Ties can be re­spaced more rapidly if chalk marks are previously placed on the base of the rail where the center or edge of each tie should come.
The amount of ballast required must be carefully determined by the roadmaster. A greater lift than necessary is a waste of money. When the ballast is distributed it must not Le mixed with old material. It must be unloaded uniformly and in such a way that it will not be wasted down the sides of the embankment. The ball􀂁t is unloaded either outside the rails or in the center of the track, depending upon whether it is un­loaded with a plow or from side-dump or center-dump cars. While bal­lasting is progressing the length of open track prepared fol' the work should be reduced to a minimum and must be watched to avoid buckling.The bolts should be loosened if necessary.
If only a light lift is to be made, the work of reballasting can be done by the regular section forces, to which a few extra men may be added, or two or three section-gangs may be combined. Even for a heavy lift the size of gang required is less than for laying rail. After the ballast is unloaded and leveled the work of ballasting or reballasting consists of surfacing, smoothing up, and trimming. General surfacing is usually understood to mean lifting the track out of face to a uniform grade line. Smoothing up means the tamping up of low joints and centers to the general level. If the lift is over 4 in. th􀂚 usual procedure is to bring the track to general surface by shovel-tamping all ties. After the track has been sett.led a few days by traffic it is gone over again and resurfaced or smoothed up, using tamping-bars or tamping-picks. The ballast is hen trimmed to the !'tandard ballast section, extra ballast is removed, and the work is finished. If the lift is in stone or slag ballast and does not exceed 4 in. the first surfacing usually is unnecessary and the ties are tamped with bars or picks. If the raise of the track is considerable, it is often done in two parts, as, for instance, a tot.al raise of lU in. might be done by making a raise of 7 in., and a final Taise of 3 in. which is tamped carefully for final surface. It may be impossible to continue the lift through tunnels and bridges and adjacent to platforms, water-tanks, etc., because of limited clearance. At the end of the lift a gradual run­off mu!3t be provided.
The usual gang contains from 25 to 40 men. For a raise of 3 in. with stone ballast and 4 or 5 tie-renewals per rail, a gang of 30 men would be organized as follows: 4 jacks with 2 men each, jackmen putting in joint­ties; 8 men renewing ties back of jacks; 12 men tamping; 2 foremen. The organization of a gang of 10 men and foreman, for a 6-in. raise and a. few tie-renewals per rail, would be as follows: 4 jacks with 2 men each, jackmen putting in ties in each half rail length; 2 men "catching up heads" or tamping ends of ties; at end of day's run the gang goes back and 4 men spike the ties and tamp inside the rail, and remainder of gang tamp outside the rail.

 Surfacing.-The work of surfacing is continual. All parts of the track, and particularly the joints, must be watched constantly for low spots, and when thei;ie develop the low ties must be brought up to surface by tamping. After completing every kind of work on the track, more or less surfacing is necessary. The work of surfacing consists entirely of tamping, with the necessary manipulation of the track. Low spots are brought to surface by raising the track with track-jacks placed under the rail-base and outside the rail. The track is lifted until the top of rail is at grade and ballast is then tamped under the ties.
- The first work of the section-gang in the spring after removing shims, is to go over the track and give the track a general running surface. By this is meant the work done to bring the track to an easy-riding surface by tamping up the low places, not much attention being given to the general surface. General surfacing must follow reballasting, laying rail, etc. One tie showing excessive rail-cutting often is an indication of lightly tamped or low adjacent tics.
In raising track both rails always should be raised simultaneously, and by the same number of jacks under each rail, the jacks being placed opposite. When surfacing is completed, the two rails on tangents must be at the same elevation. This should be determined by using a track­level. If at any time the difference in elevation of the two rails exceeds 3/8 in. the track should be resurfaced at once.

 One type of work train, perhaps the most common type, was the ballast train. On the Kingsville Divi-sion back in the early eighties, it was usually an old GP20 and a few hopper cars. The ballast train would go on duty at some siding somewhere where the work train was stashed. If it was the first day of the work train, you might actually have to get your engine out of the roundhouse track in a yard, go dig your ballast cars out of the yard, and then run your train to where the ballast needed to be dumped. You usually took only the number of hopper cars you conceivably might need in a days work, but that was probably de-termined by the maintenance-of-way foreman, and the train crew just dug out the car numbers requested. Another option might be to dig out all the cars you needed for a week's work, haul them to a house track somewhere, and only take the number of cars out on the line that you needed that day. At the end of the day, you would probably tie up in some house or team track near there, which is where you would go on duty the next day of work.
Once the ballast train was moved to where the ballast needed to be dumped, the crew's job was pretty much over with until time to stash the train somewhere. The MOW foreman would take over all the decision making for the train movements and instruct the engi-neer by radio when to ease ahead, back up, or stop.

Spreading ballast like this on the mainline was a slow time-consuming affair. The MOW crew would place a railroad tie under the car and in front of the trailing wheels of the car being unloaded. They would only unload one car at a time. They would then open the hopper under the car enough so the ballast would start flowing out, and the engineer would move the train ahead until instructed to stop. If too much bal-last came out, I would imagine they would have to shovel some out from under the car. The tie kept the ballast from getting under the wheels, and also smoothed it out to no higher than the top of the rail. Later, a tamping gang would come along and raise the track up a bit when they tamped the new ballast under the track. The reason you only took the number of cars you needed out onto the line was probably because a long string of cars has more slack, and the ballast might pile up higher underneath the cars be-fore the slack ran out, making it more difficult for the MOW crew to work the ballast. 


a spot tamping gang, needing only a Tamper and a Regulator along with a crew truck and mechanic truck

 

No comments:

Post a Comment